The St Marks Square project in Bromley is well under way. Studio Egret West is responsible for the design of both the stepping public realm and the hotel.

The concrete work for basement, ground and upper ground is complete. The entry to the lower plaza off Simpson’s Road up is now emerging, with the lower commercial units and the accessible lift core concrete works complete. Our Unit 09 that defines the eastern edge of the site has been finished up to the upper plaza level. In addition the stair that connects the lower plaza to the upper plaza was recently cast and the new entry sequence to the development is defined. The concrete columns for the next stage of post-tensioned construction are being cast soon, and the new transfer slab thereafter.